Haiti - Les Cayes Airport : Modernization work nearing completion - HaitiLibre.com : Haiti news 7/7
 Download the revised decree and electoral calendar, published in the official journal





iciHaiti - Bahamas : The Haitian Ambassador visits a Haitian church in Nassau

iciHaiti - Petit-Goâve : 2nd cohort of women graduate in fields traditionally reserved for men

iciHaïti - Elections : First day of political party registration

iciHaïti - Croix-des-Bouquets : Positive report of the 2nd day of the PNH intervention

iciHaiti - Closing Series : Results of the 1st day of the D1 national championship


more news


Haiti - News : Zapping...

Haiti - FLASH : Qatar Diaspora, Security Advice

Haiti - FLASH : Cabinet reshuffle, 11 new Ministers, 27% of whom are women

Haiti - U-20 World Cup 2027 Qualifier : Haiti vs Guyana, Grenadiers win by forfeit [3-0]

Haiti - News : Zapping...


more news


Haiti - Les Cayes Airport : Modernization work nearing completion
30/12/2025 08:31:02

Haiti - Les Cayes Airport : Modernization work nearing completion

The renovation work at Antoine Simon International Airport, launched in September, was 80% complete by mid-December, with an initial delivery date of December 31, 2025.

Compliance with international standards (TSA and ICAO) : These interventions, while temporary pending the launch of the future master plan, aim for immediate and secure operation. A crucial milestone has already been reached: in early December, the airport received approval from the Transportation Security Administration (TSA), officially opening the way for direct flights between the United States and Les Cayes. https://www.icihaiti.com/en/news-46347-icihaiti-les-cayes-good-news-for-antoine-simon-international-airport.html

A task force from the National Airport Authority (AAN) is currently deployed on-site to ensure strict compliance with standards. It is composed of :

  • The International Civil Aviation Organization (ICAO);

  • The Federal Aviation Administration (FAA);

  • The National Civil Aviation Office (OFNAC).

Main terminal improvements :

The project, carried out by the Haitian firm SD Construction S.A. under the supervision of BETA Consulting Engineers, transforms the passenger experience:

  • Improved flow :

    Repositioning of check-in counters and the Security Checkpoint (SCR);

  • Sovereign Services:

    Creation of dedicated areas for immigration (departure/arrival) and customs;

  • Comfort :

    Construction of an international departure lounge, a VIP lounge, and full terminal air conditioning;

  • Logistics :

    New baggage handling area and relocation of Sunrise Airways' ticketing/cargo services.

Security and Technical Infrastructure :

In addition to the terminal, perimeter security work is underway :

  • Installation of a temporary lighting system;

  • Construction of a Road Access and Screening Post (PARIF);

  • Imminent commissioning of technical rooms for IT and video surveillance.