Haiti - Reconstruction : Resumption of works at Toussaint Louverture International Airport - HaitiLibre.com : Haiti news 7/7





iciHaiti - Health : 60 nurses trained in obstetric emergencies

iciHaiti - Insecurity : Minister Vincent asks to use force and muscular methods

iciHaiti - PNH : Arrest of a rapist of an 11-year-old girl

iciHaiti - Politic : Prime Minister Jouthe celebrates rural women

iciHaiti - Spain : The new Ambassador of Haiti presented his Letters of Credence to King Felipe VI


more news


Haiti - News : Zapping...

Haiti - Diaspora Covid-19 : Daily bulletin October 24, 2020

Haiti - FLASH : Jovenel Moïse wants a new Constitution before the elections

Haiti - Politic : The MHAVE seeks a solution for Haitians living in Chile

Haiti - FLASH : Fuel prices revised downwards (OFFICIAL)


more news


Haiti - Reconstruction : Resumption of works at Toussaint Louverture International Airport
23/12/2017 08:04:08

Haiti - Reconstruction : Resumption of works at Toussaint Louverture International Airport
The rehabilitation of the main runway of Toussaint Louverture airport has resumed in recent weeks, after a break of almost a year. Remember that this important market won in 2015 by the consortium V & F Construction, a company of the Jean Vorbe Group and the French construction company Razel, https://www.haitilibre.com/en/news-14377-haiti-reconstruction-rehabilitation-of-runway-10-28-of-the-toussaint-louverture-airport.html which was to end during the first quarter of 2017, had been suspended at the end of 2016 by the Haitian State (prime contractor) and the works unfinished...

However, the contract has not been modified and the work to be done or completed remains the same as that set in the specifications and concerns runway 10-28, the traffic lane close to the terminal and the access ramps.

The landing and take-off runway 10-28 whose the dimensions of which before the work was 3.06 km long and 42.75 meters wide, was to widen by 60 meters, with the construction of two shoulders of 8,62 meters on each side. The traffic lane which channels the traffic to the terminal, 23 meters wide, before the work was to extend over 44 meters by adding two shoulders of 10.5 meters each. As for the access ramps, 300 meters long, they had to be fully rehabilitated, given their poor condition.

As in 2016, the work is conducted exclusively at night between 8:30 pm and before 6:00 am to take into account the air traffic during the day.

The work will take about 3 months to complete. It should be noted, however, that work on the earthworks, necessitated by the shoulders, had already been carried out before the stop. Several hundred cubic meters of material had also been excavated. The same is true of the earth movement and the stripping which had brought a volume of 738,000m3 of excavated material.

See also :
https://www.haitilibre.com/en/news-19596-haiti-reconstruction-progress-of-works-at-toussaint-louverture-airport.html
https://www.haitilibre.com/en/news-14377-haiti-reconstruction-rehabilitation-of-runway-10-28-of-the-toussaint-louverture-airport.html

HL/ HaitiLibre

Twitter Facebook Rss
Send news to... Daily news...




Why HaitiLibre ? | Contact us | Français
Copyright © 2010 - 2020
Haitilibre.com