Haiti : Access work underway at the Mont Fleury solar power plant site - HaitiLibre.com : Haiti news 7/7
 Download the revised decree and electoral calendar, published in the official journal





Jamaica : 17 Haitian Boat People intercepted

Ecovert-Haiti : Environmental emergency in Métivier

OFATMA honors the commitment of its employees

Miragoâne : The Ministry of Public Works in action

iciHaïti - Call for applications : 20 fully funded tourism scholarships


more news


Zapping Haiti of June 23, 2026

Training on the «Fundamentals of public procurement» for the benefit of MENFP executives

Haiti - Politic : Fruitful exchanges between Raina Forbin and Albert Ramdin

Haiti - Baccalaureate : Registration of gifted students (HIP)

Security : Construction of 5 forward operating bases in Port-au-Prince, Haiti


more news


Haiti : Access work underway at the Mont Fleury solar power plant site
27/04/2026 08:44:02

Haiti : Access work underway at the Mont Fleury solar power plant site

Following the signing of the contract for the construction of the Jacmel photovoltaic solar power plant at the Mont Fleury site (https://www.haitilibre.com/en/news-46650-haiti-technology-construction-of-a-major-solar-power-plant-in-jacmel.html), Joseph Almathe Pierre Louis, the Minister of Public Works (MTPTC), instructed the teams to expedite the development work on certain road sections with the technical support of the Southeast Departmental Directorate (DDSE-Jacmel). This breakthrough not only benefits the energy project but also represents a major improvement in access for the local population of Mont Fleury (6th communal section of Jacmel).

It is worth noting that the Ministry of Public Works (MTPTC) is acting as the project owner and is ensuring the rigorous supervision and monitoring of the progress of the photovoltaic solar power plant, which is being built with over $17 million in funding from the World Bank through the Renewable Energy for All in Haiti (SREP) program.

The contractor, the Dominican international firm ESD Engineering Service S.R.L., is responsible for delivering a state-of-the-art, turnkey solution. The installations will include:

• A 4 MW solar power generation capacity (minimum output of 3.35 MW);

• A 6 MWh battery energy storage system (BESS) using lithium-ion technology;

• Grid expansion with the installation of approximately 4 km of low-voltage lines and 7 km of medium-voltage (23 kV) lines.

Thanks to its grid-forming technology, this power plant will guarantee the stability of the electrical grid, even in the event of a shutdown of the current thermal power plant or during periods of low sunlight.

Construction of this power plant is expected to take 13 months, from February 2026 to March 2027.

See also :

https://www.haitilibre.com/en/news-46650-haiti-technology-construction-of-a-major-solar-power-plant-in-jacmel.html

HL/ HaitiLibre



Twitter Facebook Rss
Send news to... Daily news...




Why HaitiLibre ? | Contact us | Français
Copyright © 2010 - 2026
Haitilibre.com